08/24/2020: Our new farm will be built here.
08/24/2020: This will be the driveway.
24.08.2020
08/26/2020: Today they have
Work started on excavating the basement.
08/31/2020: Now it starts with heavy technology.
31.08.2020
August 31, 2020: The trench for the media is also in progress.
04.09.2020: Now the excavation pit is almost finished.
04.09.2020: ... and the cables are in the ditch.
07.09.2020: The ditch is closed again and the power connection is ready.
07.09.2020: A small corner is still missing to complete the construction pit.
09/10/2020: Now the excavation pit is finished. Now the basic lines have to go in.
14.09.2020: Earthworks for the underground lines
15.09.2020
09/21/2020: The ground cables and the ring earth electrode have been laid.
09/22/2020: The crane has come and is being set up.
09/23/2020: The crane is standing!
09/24/2020: The basement sub-layer has been introduced.
09/25/2020: The insulation has been installed.
09/29/2020: Probation, tape earthing and formwork are ready.
30..09.2020: The floor slab for the cellar is poured. The blinding layer for the rest of the building is in progress.
October 2nd, 2020: The formwork for the strip foundations is provided.
October 7th, 2020: Today the first part of the cellar came.
October 8th, 2020: The basement is finished.
09.10.2020
October 12, 2020: Further concreting of the strip foundations.
October 13th, 2020: The first wall in the basement is finished.
October 15, 2020: The strip foundations are ready.
10/17/2020: The basement walls are now all in place.
October 20, 2020: Today the ceiling was delivered and laid.
October 24th, 2020: The steel weavers have completed the steel work for the base plate.
10/28/2020: The floor slab was poured today.
October 29, 2020: The masonry work for the first floor began today.
November 1st, 2020: The first walls on the ground floor are in place.
November 3rd, 2020: The first front is finished.
06.11.2020
November 12th, 2020: The ground floor is ready. The supports for the ceiling are up.
November 13th, 2020: The ceiling above the ground floor has been laid.
November 16, 2020: The probation in the ceiling above the ground floor is ready.
November 19, 2020: The ceiling above the ground floor is concreted.
November 21, 2020: The outer walls were completely laid out.
11/23/2020: The interior walls are in place.
11/23/2020: The windows of the pension rooms can already be seen.
11/25/2020: The outer walls of the upper floor are almost finished.
26.11.2020
November 27, 2020: The first interior walls are on the upper floor. The boarding houses are taking shape.
11/28/2020: The pension rooms are taking shape.
28.11.2020
December 2nd, 2020: The interior walls are ready. Now the supports for the ceiling are placed.
02.12.2020
December 4th, 2020: The truck with the ceiling is ready.
04.12.2020
December 6th, 2020: The ceiling is in place, the probation and the electrics are laid.
December 9th, 2020: The ceiling is concreted.
December 10th, 2020: The two gables are bricked.
10.12.2020
December 11th, 2020: The support for the supports is finished and the first gable is formed.
11.12.2020
December 14th, 2020: The columns and the gables are concreted. Now the roof structure can come.
December 15, 2020: Precisely at 7 a.m., the truck with the roof truss rolled onto the construction site.
15.12.2020
December 15, 2020: Half of the roof structure was in place in the afternoon.
December 16, 2020: The roof structure is ready!
Today (on December 16, 2020) would be the day of the topping-out ceremony. Unfortunately we have to postpone this due to the corona. But we're catching up with the companies. Promised!
At this point it is time to say thank you to all the companies involved in the construction so far. Thanks for the speedy construction process, we only had one day off due to the rain. We, my wife and I, would like to thank the company Hoch-, Tief- und Ingenieurbau Döhnert from Hartha, and especially the foreman Frank Eichhorn and his team. Despite the shorter and shorter days, work was carried out from daylight until dark. On Saturdays, too, things went well. Our thanks also go to the Jens Weishaupt company from Freital, who punctually brought the media into the ditch. The Elektro Kraft company set up the construction site electricity so that the construction container could also be heated. The master roofer Heiko Schilling and his men will close the roof this week. Previously, carpenter Andre Böhme and his team had set up the roof structure within two days.
But our biggest thanks go to the Freital engineering firm Andreas Fischer. The head of the company of the same name has accompanied our ambitious project from the start. It was he who gave our dreams a dimension. A pencil sketch thrown loosely on paper is reminiscent of a first meeting to collect ideas. The ingenious thing about it is that it is exactly this house - changed by one or the other irrelevant detail. His employees also turned out to be just as creative as the boss. For example, they thought through the pension rooms and the associated functional rooms down to the last detail. You have identified yourself absolutely with the project and - at least ideally - brought it to life. Thanks a lot for this!
It is fun to be a builder when you can see the commitment with which our local companies do their work.
Thank you all! Kerstin & Eyk
December 18, 2020: The underlays have been laid and the house is rain and snow proof. Now all companies involved are going on the well-deserved Christmas and New Year holidays until January 3, 2021.
02/12/2021: Our construction site is currently covered with snow. But things are progressing in the house. The plumbing and electrical installation are ready. Drywall construction is progressing and when the temperature is above zero, the plasterers can start their work.
March 2nd, 2021: The roof is completely covered.
03/03/2021: The crane has done its job and will be moved to the next construction site.
March 9th, 2021: The rooms in the guesthouse are cleaned and the screed has been put in place. Now it's time to dry out ...
April 27th, 2021: The wheelchair-accessible toilet for our guests is already tiled.
04/29/2021: The guest room of our guesthouse is also tiled. The painters have started work.
05/31/2021: The facade received the external plaster today.
Our second construction phase
June 24th, 2021: The construction road is finished.
July 1st, 2021: The earthworks for the stable have started.
July 8th, 2021: The foundations for the stable are being excavated.
July 8th, 2021: The preparations for placing the extinguishing water cisterns are complete.
07/09/2021: The extinguishing water cisterns arrived with two heavy trucks and are being installed today.
09.07.2021
July 9th, 2021: The cisterns are in place in the afternoon.
07/12/2021: The crane for the second construction phase has arrived.
08/04/2021: The foundations for the stable are ready.
04.08.2021
08/18/2021: The blinding layer for the barn has been put in place.
08/25/2021: Today the floor slab for the stable was poured.
01.09.2021: The foundations for the barn are in progress.